The current transformers shall be placed around the three incoming phase conductors to the electrical panel or the facility that is to be measured and which also supplies EnergyHub. It is important that EnergyHub is connected after the current transformers seen from the mains. The figure below shows in green where the current transformers are to be mounted and also in red two incorrect locations.