Answer:
The current transformers should be installed around the three incoming phase conductors to the electrical panel or property to be measured, which also supplies the EnergyHub. It is important that the EnergyHub is connected after the current transformers, as seen from the power grid. The figure below indicates in green where the current transformers should be installed and in red, two incorrect placements.
We constantly want to improve the content in the Knowledge Database and would appreciate it if you give feedback on our articles. Does all the information exist, is there anything that needs to be clarified or is there any information that is missing that would help installing or using the EnergyHub system in general? You can give us feedback by choosing if the article was helpful or not in the options below.
If you need to get in contact with Ferroamp's Technical Support or if you have any questions about the system, you can do so by creating a ticket here.
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article