How do I expand an ESS battery with additional battery modules?

*NOTE: The information below is directed towards installers. Only trained electricians are allowed to install Ferroamp’s products.


Answer:


The ESS battery can have up to 5 modules in one stack. It's important to ensure that the existing battery is fully charged to 100% before adding any additional modules. The installation of the new battery module should be done according to the accompanying manual, which can also be found here.


We constantly want to improve the content in the Knowledge Database and would appreciate it if you give feedback on our articles. Does all the information exist, is there anything that needs to be clarified or is there any information that is missing that would help installing or using the Ferroamp system in general? You can give us feedback by choosing if the article was helpful or not in the options below. 


If you need to get in contact with Ferroamp's Technical Support or if you have any questions about the system, you can do so by creating a ticket here


  

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article